If there’s anything you need clarification on that isn’t covered here, don’t hesitate to get in touch. We’re always here to help.

What is a new grid connection?
What are the costs involved?
Can I upgrade an existing grid connection instead of applying for a new one?
What’s the difference between you, an iCP & an iDNO?
How do I know if I need a new grid connection?
How long does it take?
How do you reduce project cost?
Are iCPs and iDNOs regulated?
What information do I need to provide?
Do I need to apply for planning permission?
How do you reduce project lead time?
How do I ensure compliance with regulations during the process?

The example below illustrates a case with an e-Truck (e-HGV) operator who needed high-power DC truck charging (250kVA) at their site. However, their existing main fuse lacked the capacity to support this requirement. At the same time, they recognized that their current electrification needs were just a small fraction of what would be required in the future.

The standard solution offered to them was inflexible and costly. By contrast, our bespoke approach delivered significant savings: reducing the total project cost by 50% and the grid connection cost by 73%. Additionally, we streamlined the process, cutting the overall project timeline by an impressive 121 days (almost 4 months). This demonstrates our commitment to providing efficient, cost-effective solutions that are scalable for future needs.

FeatureStandard SolutionOur Bespoke Solution
Size of New Grid Connection (kVA)250kVA1000kVA
Supply, Install & Maintenance of New Grid Connection (£)£150,000£165,000
Asset Value (-£)£0-£125,000
Lead Time From Contact to Quote (Days)80 Days53 Days
Lead Time From Quote to Handover (Days)240+ Days (No Guarantee)146 Days
Future Upgrade Capability? (Y/N)No Spare CapacityYes, 75% Capacity Spare
Supply, Install & Maintenance of EV Charging Hardware & Software£120,000£95,000
Simple? (Y/N)No, relentless hours phoning electrician & DNOYes
Supply Chain Strength Index?Low, Limited by DNO & KnowledgeHigh, Multiple Quotes for Each Step
Bespoke Design? (Y/N)NoYes
Total Project Cost (£)£270,000£135,000
Total Project Time (Days)330+ Days209 Days

The example below highlights a case with a luxury hotel, bar, and restaurant that sought to introduce DC charging for their patrons, aiming to create a new revenue stream for the business. Alongside this, they were upgrading their kitchens from LPG gas to modern induction hobs (80kW 3-phase), a change that was expected to reduce their energy bills by over 40% and improve kitchen efficiency. However, their existing main fuse lacked the capacity to support these upgrades.

The standard solution offered was both rigid and expensive. In contrast, our tailored approach led to remarkable savings: we reduced the total project cost by 87%, and the grid connection cost became profitable, making the client £9,000, thanks to our innovative use of the DNO ‘Opportunistic Works’ system. Furthermore, we improved project efficiency by cutting the overall timeline by 65 days (roughly 2 months), delivering a faster, cost-effective solution with future scalability.

FeatureStandard SolutionOur Bespoke Solution
Size of New Grid Connection (kVA)500kVA500kVA
Supply, Install & Maintenance of New Grid Connection (£)£115,000£20,000
Asset Value (-£)£0-£29,000
Lead Time From Contact to Quote (Days)80 Days55 Days
Lead Time From Quote to Handover (Days)150+ Days (No Guarantee)100 Days
Future Upgrade Capability? (Y/N)Not required for this siteNot required for this site
Supply, Install & Maintenance of EV Charging Hardware & Software£34,000£28,000
Simple? (Y/N)No, Relentless Hours Phoning Electrician & DNOYes
Supply Chain Strength Index?Low, Limited by DNO & Electrician ExperienceHigh, Multiple Quotes for Each Step
Bespoke Design? (Y/N)NoYes
Total Project Cost (£)£149,000£19,000
Total Project Time (Days)240+ Days175 Days